What does a $4.4 billion bridge project owe a park that opened in 1909? For Goebel Park, a state project document lists the answer, with dollar amounts.
Construction on the Brent Spence Bridge Corridor broke ground May 6. Since then, most attention in MainStrasse has gone to closed ramps and detours. The project's commitment tracker, dated June 4, 2026, shows another side of it. For the parkland it uses, the project has listed specific commitments, and together they pay for much of Goebel Park's next chapter. The largest of those commitments covers water play, which Goebel Park has gone without since its pool closed for good in 2024.
What the bridge takes, and what it gives back
The project commitment tracker treats the "Goebel Park Complex" as one unit. That covers Goebel Park and the adjacent Kenney Shields Park. The project will use an estimated 2.18 acres from the complex's southwest corner, about 1.58 acres from Goebel and 0.6 acre from Kenney Shields.
It gives back an estimated 2.11 acres of state-owned land next to the complex's northwest corner. The park ends up close to its current size, but part of it moves to the other side.
Here are the main commitments for the complex, with the status the tracker gave each as of June 4, 2026:
| Commitment | What the project funds | Status in the June 2026 tracker |
|---|---|---|
| Goebel Park Complex Master Plan | About $100,000 for a community-driven plan covering at least 10 years | Design in progress |
| Replacement parkland | About 2.11 acres next to the northwest corner, replacing about 2.18 acres used | Design in progress |
| Walking trail | About 360 feet of trail rebuilt inside the complex | Design in progress; construction not started |
| Kenney Shields courts | About $94,500 to replace and enhance the basketball courts or other outdoor recreation | Not started |
| Pool | About $1,337,400 for a new outdoor pool or a comparable aquatic facility in the complex | Not started |
| Temporary courts | Up to $75,000 for a temporary facility elsewhere in the complex if the courts are affected before replacements are built | Not started |
The tracker leaves the layout to the city. The new pool or aquatic facility and the replacement courts will be placed "as established during the new master planning process facilitated by the City of Covington." The trail's new route will be set in coordination with the city during the project's final design. The bridge project supplies the money, and the master plan decides how it lays out on the ground.
A September 2026 project re-evaluation adds a smaller piece. Once the West Fifth Street overpass is demolished, that area will become part of the Goebel Park Complex.
The pool line is the one to watch
The $1.34 million figure stands out because of the park's recent history. LINK nky reported in April 2024 that Goebel Pool had closed for good after the Covington Board of Commissioners left it out of that year's aquatic-facility service agreement.
The bridge commitment is technically compensation for "proximity impacts to the existing outdoor pool." For a park whose pool had already closed, that money is a funded path back to water play. The wording also leaves room in the design. It allows a new outdoor pool "or other comparable aquatic facility serving the same recreational purpose."
That flexibility matters because of what residents said they wanted.
What 412 surveys asked for
Covington's Division of Parks & Recreation hired the Cincinnati firm KZF Design to lead the master plan, and the Board of Commissioners approved the contract late last year. When the process started this spring, Parks and Recreation Manager Greg Stacy described the pressure on the park plainly to WVXU:
"It's going to be forced to kind of change with this new Brent Spence bridge project, some of the borders of the park are going to be shifted."
At the in-person open house on July 28 at the Hellmann Creative Center, KZF Design Director of Planning Abby Stainfield said the team had received 412 completed surveys, according to LINK nky's coverage of the event. These were the themes that came out on top:
- Nature, including keeping what is already there and adding green and natural areas
- Better neighborhood connections for walking and biking to the park and through it
- Making the park a destination
- Embracing the park's history, including preserving the bell tower
- Safety through lighting and wayfinding
- Nature play areas
- A water feature, either a splash pad or a sprayground
Several of those requests already have money attached. The water feature lines up with the $1.34 million aquatic commitment, and better walking connections line up with the rebuilt trail. The preliminary renderings shown in July point the same way. Goebel's side got the quieter, natural uses, an event lawn and a nature play area. Kenney Shields got the active ones, basketball and pickleball courts, which matches where the $94,500 court commitment goes.
The bell tower is the one big request without a specific dollar figure in the tracker. The city's stated scope for the plan includes planning "for the future of the Bell Tower," alongside better connections and reworking underused spaces. WVXU reported in April that the Carroll Chimes Bell Tower clock was not working at the time and that many survey responses asked to have it fixed.
Where the plan stands this week
The online Recommendations Open House closed September 2. KZF's project page lays out three phases, and the July open house belonged to the second:
- Project Initiation and Input Gathering. Park tours, data collection and the first survey round.
- Analysis and Visioning. Draft concepts, working sessions with city staff and the stakeholder committee, and a second round of public input.
- Final Plan and Implementation Strategy. Refined recommendations, set priorities, cost projections and timelines, and the final plan prepared for City review and adoption.
The third phase is where the trade-offs get settled, including where water play goes and what happens to the bell tower. Stainfield told the July crowd that the goal is a phased plan "so the city can kind of start off on the right foot when they go to look at funding for the next project." The KZF engagement site holds the July renderings and is the place to watch for the final draft. The tracker also requires the master plan to be finished within a year of the planning process starting.
Getting to the park this winter
The changes to the park's edges are already visible from the street. As of mid-November, these are the access points that matter for Goebel Park and MainStrasse:
- Southbound I-71/75 at Exit 192 now lets out only onto Crescent Avenue. The southbound exit to W. Fifth Street has closed permanently. KYTC's posted detour to W. Fifth Street goes right on Crescent, right on Third Street, then right on Philadelphia Street.
- W. 9th Street is closed between Crescent Avenue and Willow Run Road in both directions through substantial project completion, expected in 2033. Pedestrians walking from Goebel Park use the posted route via Western Avenue, Philadelphia Street, W. Pike Street and Lewis Street.
- The northbound exit road onto Fifth Street will be shortened to make room for work in Goebel Park, LINK nky reported on November 9.
- The W. Fifth Street pedestrian overpass stairs near the inactive community garden were scheduled for demolition in November 2026. The plan calls for one day of demolition and one to three days to restore the disturbed area.
- The 0.8-mile Riverwalk detour between Madison Avenue and Wright Street sends trail users along Rivercenter Boulevard, West Third Street and Highway/Crescent Avenue. It stays in place until the companion bridge is finished, currently anticipated in 2031.
There are a few changes coming too. KYTC spokesperson Jake Ryle told LINK nky that the first reopening will be the southbound on-ramp to I-71/75 from 12th Street, possibly within the next few months. The old 4th Street northbound on-ramp will also reopen. When it does, the Texas turnaround and the Pike Street northbound on-ramp will close permanently. Ryle said official announcements will come about a month before each change, and KYTC's project manager described the closures as "stair steps" that won't happen at the same time. The Kentucky travel updates page is the one to bookmark.
A reason to be on the Sixth Street Promenade on December 5
The first holiday date on the calendar is in MainStrasse Village itself. Cov Craft is holding its first-ever holiday makers market on Saturday, December 5, from 10 a.m. to 4 p.m. on the Sixth Street Promenade in MainStrasse Village. It's free, and the announcement points visitors to Handzy Shop + Studio at 421 W. 6th St. According to the Cov Craft announcement, Covington's annual Christkindlmarkt is the following weekend.
The shops around the park have support during the construction years. More than 30 businesses had enrolled in the city's "Bridging the Gap" initiative by late March, FOX19 reported. The program promotes local businesses and events and adds wayfinding. The Commonwealth has also set aside $750,000 for Covington over five years for business promotion, public information and neighborhood connectivity while the bridge is built, LINK nky reported.
A park that gets a new layout, water play and a gateway role also changes how the homes around it present, from the view out the front window to the walk to the Promenade. If you own near Goebel Park and want to know how its next chapter could affect your home's value, Paige Von Hoffmann and the LIVIN IN CIN team can walk you through it. Request your personalized home valuation, and we'll factor in the street you're on today and the park plan taking shape next to it.